From Monday, March 16, 2006 Week Two, Day Four
Most of the drywall has been completed. Our expectation is that we will complete our dry-walling tasks tomorrow (Friday). We had six teams of five working to install and finish drywall today. The kitchen will be ready for cabinets soon after the next crew arrives. The island plumbing in the kitchen is currently being re-worked and should be finished tomorrow (Friday) morning. We are continuing to enjoy each other, the food and the devotions. God's richest blessings to all,
Editors note: The funds continue to flow in for this project. The Indiana Area Foundation has received $72,024. The project needs $127,976 to be completed. Thank you for your generous contributions. DRG Last updated on April 08, 2008 |
|